Projects ranked by estimated investment (KES)
| # | Proposed Project | Activities | Ward | Department | Type | Status | Estimated Cost (KES) | FY |
|---|---|---|---|---|---|---|---|---|
| 1839 | Purchase of 3 tonne wheel loader machine for the ward | Purchase and delivery of a 3 tonne wheel loader | Kee | WSI | Hard | New | 12,000,000.00 | 2026/2027 |
| 1921 | Kikima town and Markets improvement programme | Cabro paving of walkways, streetlightning,market lighting ,construction of bodaboda shed and fencing of Kikima town ECDE | Mbooni | INFRA | Hard | Ongoing | 10,000,000.00 | 2026/2027 |
| 1697 | Kibwezi borehole | Extension of water pipeline accross the ward | Masongaleni | WSI | Hard | Phased | 10,000,000.00 | 2026/2027 |
| 1706 | Metava Borehole | Drilling, Equipping and distribution | Thange | WSI | Hard | New | 10,000,000.00 | 2026/2027 |
| 1553 | Construction of 4 ECDEs (Ng'oi, Ngukuni, Kyangwasi & Maumba) each @ 2.3 million shillings | Construction of 1 classroom and office in each school | Nzaui/Kilili/Kalamba | DIEI | Hard | New | 9,200,000.00 | 2026/2027 |
| 1674 | Ward road's improvement & machine hire | murraming, grading, gravelling &drift construction | Mtito Andei | INFRA | Hard | New | 8,000,000.00 | 2026/2027 |
| 1490 | Katheka and Mbuthani ECDE classes | Construction of 2 ECDE Classrooms, office, store, 3 door pit latrine with urinal, shelving,equipping, 2 pinned boards,whiteboard with accessories,office table, executive chair, 20 kiddy chairs & tables, conduits works installation, water harvesting and outdoor equipments. | Mbitini | DIEI | Hard | New | 7,200,000.00 | 2026/2027 |
| 1870 | Thwake Sand Dam | Distribution pipeline and construction of water kiosks | Tulimani | WSI | Hard | Phased | 6,350,000.00 | 2026/2027 |
| 1938 | Ngoni Earthdam solarization & distribution | solarization & distribution | Kisau/Kiteta | WSI | Hard | New | 6,150,000.00 | 2026/2027 |
| 1581 | Road improvenment + structures | Grading and opening of feeder roads across the ward+ road structures (culverts, gabions & rataining walls) | Kikumbulyu North | INFRA | Hard | New | 6,000,000.00 | 2026/2027 |
| 1672 | mang'elete extension | construction of elevated tank, distribution to (miangeni, kathekani, mtito Andei, nthunguni & kyusyani | Mtito Andei | WSI | Hard | Phased | 6,000,000.00 | 2026/2027 |
| 1945 | Roads Maintenance- Light Grading and spot Murraming with Miradi Kwa Jamii (MKJ) Programme | Light Grading and spot Murraming with Miradi Kwa Jamii (MKJ) Programme | Kisau/Kiteta | INFRA | Hard | New | 6,000,000.00 | 2026/2027 |
| 1796 | Matuua/Mitini road | Construction of Drift/ | Kilungu | INFRA | Hard | New | 5,000,000.00 | 2026/2027 |
| 1556 | Opening and grading of roads | Road maintenance | Nzaui/Kilili/Kalamba | INFRA | Hard | New | 5,000,000.00 | 2026/2027 |
| 1559 | Piping and distribution of 6 water projects in the ward (Kalima, Kaiani, Ithetheni, Makuli, Lang'a and Kyangaatu water projects) | Water distribution | Nzaui/Kilili/Kalamba | WSI | Hard | New | 5,000,000.00 | 2026/2027 |
| 1580 | table banking at village level | support to table banking groups at village level | Kikumbulyu North | GCYSS | soft | New | 5,000,000.00 | 2026/2027 |
| 1915 | Kwa Kavoi- Iimbani-Yamutundu road | Opening of the road | Kithungo/Kitundu | INFRA | Hard | New | 5,000,000.00 | 2026/2027 |
| 1924 | Mitangani/Kwa Nzembi slab and rehabiltation of Ngungu gulley | Construction of slab and gulley rehabilitation | Mbooni | INFRA | Hard | New | 5,000,000.00 | 2026/2027 |
| 1935 | Equiping of Syumbe/kanyenyoni B/H | Equipping with solar pumping system and point water kiosk | Kisau/Kiteta | WSI | Hard | Non operational | 5,000,000.00 | 2026/2027 |
| 1709 | AIC Mbulutini-Kivondo-Ngumbi-AIC Thange-Mwandoko-Isunguluni-Kwa Nicko-Kinyambu school-Makongeni-Veneti-Msa Road | Murraming, construction of road structures and drifts | Thange | INFRA | Hard | New | 5,000,000.00 | 2026/2027 |
| 1732 | Musengoni borehole | Drilling, equiping and distribution | Kiima Kiu/Kalanzoni | WSI | Hard | New | 5,000,000.00 | 2026/2027 |
| 1734 | Kyamuloi Borehole | Drilling, equiping and distribution | Kiima Kiu/Kalanzoni | WSI | Hard | New | 5,000,000.00 | 2026/2027 |
| 1518 | Road grading and maintainance of all roads across the ward | Road grading and maintainance across the ward. | Mavindini | INFRA | Hard | New | 5,000,000.00 | 2026/2027 |
| 1787 | Maintainance and opening of these roads;1.)Kyamumangi-malindi-Kyamulinge 2.)Manyanzala-Matwiku-Kitheini 3.)Kyaseke-kyakatungu-kyang'a 4.)Mutomboa-muchamo-muangini 5.)Mwaani-Kyangatia-mowe 6.)Wautu -ivia yiu-kikongooni 7.)Ngunga-syathani 8.)ACK Mutomboa - kwa kongo 9.)Kyesuni-katondoloni-mbusyani-kwa rachael. 10. Kyang'a -Kithangathini- Kituiuni | Opening, grading and spot murraminng | Ilima | INFRA | Hard | New | 5,000,000.00 | 2026/2027 |
| 1875 | ECDE Kwaithi | Construction of ECDE classes Kwaithi | Tulimani | DIEI | Hard | New | 4,500,000.00 | 2026/2027 |
| 1876 | ECDE Nthangathini | Construction of ECDE classes Nthangathini | Tulimani | DIEI | Hard | New | 4,500,000.00 | 2026/2027 |
| 1893 | Ngomano/Uviluni Water Project:Phase 1:Construction of sump in Ngomano , Raising Main from source and Connection to an existing distribution system | Ngomano/Uviluni Water Project:Phase 1:Construction of sump in Ngomano , Raising Main from source and Connection to an existing distribution system | Kako/Waia | WSI | Hard | New | 4,500,000.00 | 2026/2027 |
| 1916 | Ndauni-Kitonyini road | Opening and construction of drift- 7km | Kithungo/Kitundu | INFRA | Hard | New | 4,500,000.00 | 2026/2027 |
| 1664 | Construction of new outpatient block for Kiboko Dispensary | Construction of consultation room, examination room, MCH, pharmacy, store and laboratory | Makindu | HS | Hard | New | 4,500,000.00 | 2026/2027 |
| 1665 | Construction of Makindu Township Dispensary | Construction of consultation room, examination room, MCH, pharmacy, store and laboratory | Makindu | HS | Hard | New | 4,500,000.00 | 2026/2027 |
| 1702 | Ngwata health centre | Construction of an hospital block | Masongaleni | HS | Hard | New | 4,500,000.00 | 2026/2027 |
| 1703 | Masongaleni health centre | Construction of a mortuary block | Masongaleni | HS | Hard | New | 4,500,000.00 | 2026/2027 |
| 1853 | Installation of drainage structures (Box Culverts) along Mau, Hitu and Kwa Mathenge Streams | Installation of drainage structures | Kalawa | INFRA | Hard | — | 4,300,000.00 | 2026/2027 |
| 1892 | Sakai ECDE block: Construction of 2no. ECDE Classrooms with an office & store,3-Door Pit Latrine with Urinal, Electrical conduit, shelving to the stores, lockable metallic cabinet, Wooden Desk, Wooden Arm Chairs, Water harvesting goods (10,000Ltrs Water Tank and base), 40 No. Kiddy chairs and 20. No. Kiddy tables, Play equipment 4 piece set (double swing, slide, climbing frame and double see-saw), Display soft board and Branding, Publicity and Signwriting | Sakai ECDE block: Construction of 2no. ECDE Classrooms with an office & store,3-Door Pit Latrine with Urinal, Electrical conduit, shelving to the stores, lockable metallic cabinet, Wooden Desk, Wooden Arm Chairs, Water harvesting goods (10,000Ltrs Water Tank and base), 40 No. Kiddy chairs and 20. No. Kiddy tables, Play equipment 4 piece set (double swing, slide, climbing frame and double see-saw), Display soft board and Branding, Publicity and Signwriting | Kako/Waia | DIEI | Hard | New | 4,200,000.00 | 2026/2027 |
| 1540 | Nzueni borehole | Replacement of pipes and extensions | Kikumini/Muvau | WSI | Hard | New | 4,000,000.00 | 2026/2027 |
| 1544 | Ngutwa-kaseve roads | Opening,grading, water structures | Kikumini/Muvau | INFRA | Hard | Ongoing | 4,000,000.00 | 2026/2027 |
| 1549 | Youth empowerment-ligi mashinani | Youth programme ligi mashinani pwd empowerment | Kikumini/Muvau | GCYSS | Soft | Ongoing | 4,000,000.00 | 2026/2027 |
| 1568 | water tanks at Soko Muyo and Kwa Kinyae | Constrution of 2 No. 100 Cubic Meter water tanks | Kikumbulyu North | WSI | Hard | New | 4,000,000.00 | 2026/2027 |
| 1604 | Kwa Nzele water project | Distribution,2 water kiosks and one tank | Emali/Mulala | WSI | Hard | Ongoing | 4,000,000.00 | 2026/2027 |
| 1605 | Kwa Kamba water project | Equipping with solar, distribution and water kiosk | Emali/Mulala | WSI | Hard | Ongoing | 4,000,000.00 | 2026/2027 |
| 1606 | Kiuani borehole | Equipping with solar, water kiosk and distribution | Emali/Mulala | WSI | Hard | New | 4,000,000.00 | 2026/2027 |
| 1862 | Distribution of AKWASH water to Kavumbu through Mutanda | Water distribution to Kavumbu through Mutanda | Kalawa | WSI | Hard | New | 4,000,000.00 | 2026/2027 |
| 1609 | Mulala dispensary | Construction of a dispensary | Emali/Mulala | HS | Hard | New | 4,000,000.00 | 2026/2027 |
| 1625 | Road improvement along Kalakalya junction-Kwa Nzambu-Kumbo-Kakuyuni-Kalakalya catholic-Kwa Mbilu junction-Kwa Nzioka Road | Opening, grading and gravlling of Kalakalya junction-Kwa Nzambu-Kumbo-Kakuyuni-Kalakalya catholic-Kwa Mbilu junction-Kwa Nzioka Road | Nguumo | INFRA | Hard | New | 4,000,000.00 | 2026/2027 |
| 1891 | Miau Water Project:Installation of 100M^3 Masonry tank at Kwakatheo and Return Pipe. Distribution to Ngovu Market | Miau Water Project:Installation of 100M^3 Masonry tank at Kwakatheo and Return Pipe. Distribution to Ngovu Market | Kako/Waia | WSI | Hard | Phased | 4,000,000.00 | 2026/2027 |
| 1898 | Kaseveni Malamuni Road: Road Opening and Grading | Kaseveni Malamuni Road: Road Opening and Grading | Kako/Waia | INFRA | Hard | New | 4,000,000.00 | 2026/2027 |
| 1923 | Roads maintenance /improvement programme | Maintenance of existing roads, installation of culverts, structures, grading and murraming | Mbooni | INFRA | Hard | Ongoing | 4,000,000.00 | 2026/2027 |
| 1671 | Kambu/kiteng'ei wp extension | extension to Nzoila primary/secondary to Nzoila dispensary and rehabilitation of kawangware kiosk | Mtito Andei | WSI | Hard | Phased | 4,000,000.00 | 2026/2027 |
| 1687 | Nthongoni Hospital Xray | construction of xray room | Ivingoni/Nzambani | HS | Hard | New | 4,000,000.00 | 2026/2027 |
| 1689 | Aggrigation centre/ cold room | construction in phases | Ivingoni/Nzambani | AGRI | Hard | New | 4,000,000.00 | 2026/2027 |
| 1692 | Nzambani water target | distribution of water | Ivingoni/Nzambani | WSI | Hard | New | 4,000,000.00 | 2026/2027 |
| 1714 | Tents | Purchase of tents | Thange | GCYSS | soft | New | 4,000,000.00 | 2026/2027 |
| 1725 | machine hire | Kwa Rose Museo, Kwasondi - Kwakavita, Kwawakata -Mutiluni - Kwa Ngumu, Kyangala-Matumbini- Enzai Road, Kanini Kaseo -Kwa Ngumu Roads. Mwanyani - Kyangala, Kyandue Ndomino - Mukaa, Mwaani - Kwamisi - Kathemboni, Upete - Yumbuni-Kwa Mutungi - Kathemboni - Kwa Kavoo - Kwa Mwao, Mwaani - Kenze - Upete Road | Mukaa | INFRA | Hard | New | 4,000,000.00 | 2026/2027 |
| 1474 | Fuel for routine road maintenance | Inhouse fuel for road maintenance | Kitise/Kithuki | INFRA | Soft | New | 4,000,000.00 | 2026/2027 |
| 1737 | Kwa Kavesa drift | constructin of drift | Kiima Kiu/Kalanzoni | INFRA | Hard | New | 4,000,000.00 | 2026/2027 |
| 1484 | Supply of certified maize seeds. | Distribution of certified seeds ( Nduma 43) | Mbitini | AGRI | Soft | New | 4,000,000.00 | 2026/2027 |
| 1492 | Mungyani health centre | Construction of outpatient block | Mbitini | HS | Hard | New | 4,000,000.00 | 2026/2027 |
| 1494 | Road improvement programme | Fuel for road maintenance across the ward | Kathonzweni | INFRA | Soft | New | 4,000,000.00 | 2026/2027 |
| 1504 | Miusi ili borehole | Rehabilitation, solarization and distribution of Muisi ili borehole to Katangi and Mbuvo market | Kathonzweni | WSI | Hard | New | 4,000,000.00 | 2026/2027 |
| 1509 | Kwa Kavisi health centre maternity wing | Construction of a maternity wing and equipping | Kathonzweni | HS | Hard | New | 4,000,000.00 | 2026/2027 |
| 1785 | Kyambeke Market Cabro paving | Cabro paving and drainage works at Kyambeke Market | Ilima | TRD | Hard | New | 4,000,000.00 | 2026/2027 |
| 1531 | Kyenze highway- kyambui-mbuluto-koffi annan- kwa kithome-mutheeti-mikwani-mlolongo- aic kavila | Opening, grading and structures | Wote/Nziu | INFRA | Hard | New | 4,000,000.00 | 2026/2027 |
| 1788 | 1.Isovya-Kambuku-Kiongwani-Mumbuni 2.Kavutini-Katitu -milavutini 3.Kavatanzou-ABC-Mutambukoni 4.Musalala-Nthangathini-Kyenzeni 5.Inyokoni-AIC-Silanga roads | Opening, grading and spot murraminng | Ilima | INFRA | Hard | New | 4,000,000.00 | 2026/2027 |
| 1789 | Dairy Value Chain improvement | Provision of dairy cattles | Ilima | AGRI | Soft | New | 4,000,000.00 | 2026/2027 |
| 1666 | Kanaani ECDE | Construction of 2 ECDE Classrooms, office, store, 3 door pit latrine with urinal, shelving,equipping, 2 pinned boards,whiteboard with accessories,office table, executive chair, 20 kiddy chairs & tables, conduits works installation, water harvesting and outdoor equipments | Makindu | DIEI | Hard | New | 3,800,000.00 | 2026/2027 |
| 1742 | Mung'ala ECDE | Construction of ECDE classroom and equiping | Kiima Kiu/Kalanzoni | DIEI | Hard | New | 3,700,000.00 | 2026/2027 |
| 1743 | Kwa Ngumu ECDE | Construction of ECDE classroom and equiping | Kiima Kiu/Kalanzoni | DIEI | Hard | New | 3,700,000.00 | 2026/2027 |
| 1520 | Makutano ECDE | construction and equipping of ECDE(2 classrooms,store,office and equipping) | Mavindini | DIEI | Hard | New | 3,600,000.00 | 2026/2027 |
| 1583 | Construction of ECDE classroom at Yikivala | Construction of ECDE classroom at Yikivala | Kikumbulyu North | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1592 | Kevanda ECDE Class | Consruction of two classes,office,store and toilet | Kikumbulyu South | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1860 | Ngunini Dispensary - construction of a new dispensary and a toilet | Construction of a new dispensary and a toilet | Kalawa | HS | Hard | — | 3,500,000.00 | 2026/2027 |
| 1871 | Lower Ngwani Water Project | Desilting, protection gabbions, distribution pipeline and construction of water kiosks | Tulimani | WSI | Hard | Non operational | 3,500,000.00 | 2026/2027 |
| 1638 | Construction of Makasa ECDE | Construction of Makasa Ecde | Nguu/Masumba | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1639 | Construction of Mwalili ECDE | Construction of Mwalili ECDE | Nguu/Masumba | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1667 | ABC Nguuni ECDE Classroom | Construction of 2 ECDE Classrooms, office, store, 3 door pit latrine with urinal, shelving,equipping, 2 pinned boards,whiteboard with accessories,office table, executive chair, 20 kiddy chairs & tables, conduits works installation, water harvesting and outdoor equipments | Makindu | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1688 | Muthingiini staff quarters | construction | Ivingoni/Nzambani | HS | Hard | New | 3,500,000.00 | 2026/2027 |
| 1464 | Kitise water project | Genset, control panel, changer unit, cabbles and accessories, genset housing | Kitise/Kithuki | WSI | Hard | Phased | 3,500,000.00 | 2026/2027 |
| 1729 | Enzai CTTI | Construction of dormitory | Mukaa | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1736 | Kaluli, Malu, Kiu and Mung'ala | Opening, grading and Structures | Kiima Kiu/Kalanzoni | INFRA | Hard | New | 3,500,000.00 | 2026/2027 |
| 1505 | Kathonzweni HGM ECDE | Construction of two classrooms with an office and a store, water tank installation and equipping. | Kathonzweni | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1506 | Kituluni ECDE | Construction of two classrooms with an office and a store, water tank installation and equipping | Kathonzweni | DIEI | Hard | New | 3,500,000.00 | 2026/2027 |
| 1591 | Hospital bills | Payment of hospital bills | Kikumbulyu South | HS | Soft | New | 3,300,000.00 | 2026/2027 |
| 1466 | Kimundi/Kithuki water project | Rehabilitation of existing sump,rising main pipeline to kithuki market and servicing of pumping system | Kitise/Kithuki | WSI | Hard | New | 3,300,000.00 | 2026/2027 |
| 1947 | Construction of Katuma ECDE class | Construction of 2 classrooms, office, store, 10,000L water tank and a 3 door pit latrine with a urinal | Kisau/Kiteta | DIEI | Hard | New | 3,250,000.00 | 2026/2027 |
| 1487 | Roads mantainance across the subward. | Road grading across the ward | Mbitini | INFRA | Hard | New | 3,250,000.00 | 2026/2027 |
| 1657 | Upgrading of Kamboo Health Centre- Fencing and construction of maternity | Upgrading of Kamboo Health Centre- Fencing and construction of maternity | Makindu | HS | Hard | — | 3,200,000.00 | 2026/2027 |
| 1948 | Construction of Ndumbi ECDE class | Construction of 2 classrooms, office, store, 10,000L water tank and a 3 door pit latrine with a urinal | Kisau/Kiteta | DIEI | Hard | New | 3,200,000.00 | 2026/2027 |
| 1723 | ianduani ECDE | Construction of: - 1No. ECDE Classroom with an office and Store Electrical Works, Shelving to the stores, 1No. wooden desks, 1No. wooden arm chairs, water harvesting goods (10,000Ltrs water tank and base), 20No. Kiddy chairs and 10No. Kiddy tables, Play equipment 4-piece set (double swing, slide, climbing frame and double see-saw), display soft pin board, white board & mark pen, Branding, publicity and signwriting, 3- Door Pit Latrine with Urinal | Mukaa | DIEI | Hard | New | 3,200,000.00 | 2026/2027 |
| 1724 | mbukuni ECDE | Construction of: - 1No. ECDE Classroom with an office and Store Electrical Works, Shelving to the stores, 1No. wooden desks, 1No. wooden arm chairs, water harvesting goods (10,000Ltrs water tank and base), 20No. Kiddy chairs and 10No. Kiddy tables, Play equipment 4-piece set (double swing, slide, climbing frame and double see-saw), display soft pin board, white board & mark pen, Branding, publicity and signwriting 3- Door Pit Latrine with Urinal | Mukaa | DIEI | Hard | New | 3,200,000.00 | 2026/2027 |
| 1538 | Road maintainance | Grading programme | Wote/Nziu | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1542 | Kwa muia earthdam | Construction of weir and fencing | Kikumini/Muvau | WSI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1798 | Kikoko ECDE classes | Construction of ECDE classes | Kilungu | DIEI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1807 | Ndiani water project | Construction of Substation and raising main | Kilungu | WSI | Hard | Existing | 3,000,000.00 | 2026/2027 |
| 1810 | Kitituni , Nthaeni, Kwa muthiani,Kioko, kwa ngao, kyaini, kwa mukuta dispensary to kikuyuni | Murriming and structures | Kilungu | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1815 | Nunguni ECDE classes | Construction of ECDE classes | Kilungu | DIEI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1560 | Yanthooko water project | Construction and distribution | Nzaui/Kilili/Kalamba | WSI | Hard | Existing | 3,000,000.00 | 2026/2027 |
| 1840 | Fuel and maintenance of the ward wheel loader machine, operator and supervision facilitation. | Fuel and maintenance of the ward wheel loader, operator and supervision facilitation. | Kee | WSI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1842 | Grading of ward roads | Grading of the ward roads | Kee | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1848 | Miradi Kwa Jamii | Road opening, light grading, mitre drain excavation, bush clearing through casual labour | Kee | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1595 | Sports | Support to Ligi Mashinani | Kikumbulyu South | GCYSS | soft | New | 3,000,000.00 | 2026/2027 |
| 1596 | Tents and Chairs | Support to SHG groups with Tents and Chairs | Kikumbulyu South | GCYSS | soft | New | 3,000,000.00 | 2026/2027 |
| 1863 | Kathulumbi Modern Health Centre | Construction of twin wards (Male & Female) | Kalawa | HS | Hard | New | 3,000,000.00 | 2026/2027 |
| 1608 | Opening, murramimg and grading of roads | opening of roads and murraming | Emali/Mulala | INFRA | Hard | Ongoing | 3,000,000.00 | 2026/2027 |
| 1610 | Emali model health center | Construction of a theater block | Emali/Mulala | HS | Hard | New | 3,000,000.00 | 2026/2027 |
| 1624 | Road improvement along Emali Catholic-Tuanga-Maliti-Kasengo-Kwa Kitui Nzenze-Kwa Munyolo road | Opening, grading and gravelling of Emali Catholic-Tuanga-Maliti-Kasengo-Kwa Kitui Nzenze-Kwa Munyolo road | Nguumo | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1634 | Ward Administration Block | Construction of Ward Administration Block | Nguumo | DEV | Hard | New | 3,000,000.00 | 2026/2027 |
| 1637 | Kikuu Katangini WP (distribution to kisayani mrkt and kwa Mutaki. | Kikuu Katangini WP (distribution to kisayani mrkt and kwa Mutaki. | Nguu/Masumba | WSI | Hard | Phased | 3,000,000.00 | 2026/2027 |
| 1895 | Mituvu Nthatwa Kathamba Road: Construction of slabs | Mituvu Nthatwa Kathamba Road: Construction of slabs | Kako/Waia | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1904 | Mwenyeani water Pjocet | Solarization and fencing | Kithungo/Kitundu | WSI | Hard | Phased | 3,000,000.00 | 2026/2027 |
| 1905 | Munyuuka playground | Levelling of the playground and protection works | Kithungo/Kitundu | GCYSS | soft | Phased | 3,000,000.00 | 2026/2027 |
| 1655 | Ligi Mashinani | Ligi mashinani | Nguu/Masumba | GCYSS | soft | Ongoing | 3,000,000.00 | 2026/2027 |
| 1682 | Kitheini ECDE | construction of 2 classrooms | Ivingoni/Nzambani | DIEI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1683 | Nzambani ECDE and Kikwasuni ECDE | construction of 1 class each | Ivingoni/Nzambani | DIEI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1708 | Maridadi-Mutisya Ndambuki-Maweu-Peter Mukenga-Kimondiu-Makumbi-Mitooni-Nyamai | Murraming, construction of road structures and drifts | Thange | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1710 | ECDE Class at UTIITHI & KASASULE | Construction | Thange | DIEI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1722 | Mukaa Boys BH | Equiping of the borehole and metered connection to Mukaa boys and distribution to tuumini,Kamwelani,Kavita A&B, Kavila,Kavuti,Kitonguni villages. construction of main tank at Kwa Muthai | Mukaa | WSI | Hard | Phased | 3,000,000.00 | 2026/2027 |
| 1468 | Kiuuku dispensary | Construction of new outpatient block | Kitise/Kithuki | HS | Hard | New | 3,000,000.00 | 2026/2027 |
| 1726 | kwa kavoi - kavila road | granding and roads structures | Mukaa | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1727 | upete- kwa kyambu road | granding and roads structures | Mukaa | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1475 | Kikome-Kwanyaa road | opening, Grading and installation of road structures | Kitise/Kithuki | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1731 | mwalano dispensary | electrification, fencing & gate and staff house | Mukaa | HS | Hard | New | 3,000,000.00 | 2026/2027 |
| 1481 | Kithumani water project | Installation of submissive pump, Solarization and distribution to Kithumani market and Kithumani primary school | Mbitini | WSI | Hard | Phased | 3,000,000.00 | 2026/2027 |
| 1488 | Kwa Muswii- Kavuthu-Ikuyuni- Kyumbuni road construction. | Road grading, murraming and installation of road strucures. | Mbitini | INFRA | Hard | New | 3,000,000.00 | 2026/2027 |
| 1493 | Fuel and maintenance of the ward backhoe | Fuel and maintenance of the ward backhoe | Kathonzweni | WSI | Soft | Ongoing | 3,000,000.00 | 2026/2027 |
| 1514 | Kanthuni borehole water project | Distribution line from kwa muindi wa ngungi-kwa kinyanzui to kwa Maria | Mavindini | WSI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1515 | Kanyonga borehole water project | Pipeline extension from Kasayani to MethoUvini ECDE | Mavindini | WSI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1516 | Kwa Kinyao borehole water project | Drilling of borehole. | Mavindini | WSI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1525 | Kaiti-kamunyii water project | Installation of hdpe raising main | Wote/Nziu | WSI | Hard | Stalled | 3,000,000.00 | 2026/2027 |
| 1527 | Kwa masinga-kwa kasimba-nzove-makolongo-kavingo-kwa ndambuki-kwa kikuvi-iviani aic-public works (unoa | Opening, grading and structures | Wote/Nziu | INFRA | Hard | Phased | 3,000,000.00 | 2026/2027 |
| 1528 | Ikomba water project | Spring development and distribution | Wote/Nziu | WSI | Soft | New | 3,000,000.00 | 2026/2027 |
| 1529 | Kiti-kyumu dispensary | Fencing and construction of staff quarters | Wote/Nziu | HS | Hard | New | 3,000,000.00 | 2026/2027 |
| 1530 | Kituasi water project | Extension of the pipeline | Wote/Nziu | WSI | Hard | New | 3,000,000.00 | 2026/2027 |
| 1795 | Nthangathini ECDE | Construction of one class and office | Ilima | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1541 | Kyemole ecde | Construction of one classroom | Kikumini/Muvau | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1797 | Usi Uasa | Solarization, raising the weir wall and distribution to Kyanganda dispensary | Kilungu | WSI | Hard | Existing | 2,500,000.00 | 2026/2027 |
| 1543 | Makutano ecde | Construction of one classroom | Kikumini/Muvau | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1546 | Kathuma ecde | Construction of one classroom | Kikumini/Muvau | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1548 | Itaa ecde | One classroom | Kikumini/Muvau | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1850 | Ikalyoni ECDE | Construction of one classroom with an office, store and equipping | Kee | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1597 | FBOs chairs | Support to FBOs with Chairs | Kikumbulyu South | GCYSS | soft | New | 2,500,000.00 | 2026/2027 |
| 1859 | Athi Kalawa water supply project | Rehabilitation of water tank and Improvement /rehabilitation of Mukuku market to Syotuvali Market distribution line | Kalawa | WSI | Hard | Ongoing | 2,500,000.00 | 2026/2027 |
| 1611 | Grass root sports development- ligi mashinanai | Support sports activities in the ward | Emali/Mulala | GCYSS | soft | Ongoing | 2,500,000.00 | 2026/2027 |
| 1614 | Kalima ECDE | Construction of ECDE classroom | Emali/Mulala | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1615 | Kitandi ECDE | Construction of ECDE classroom | Emali/Mulala | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1873 | Roads maintenance of major roads | Roads maintenance of : 1.Kwa nzakayo-nthangathini-ndolo-kyanguswi road.2, kwa kivaya-kinganyangani-kyamithenge road,3ngunini-kyamithenge-katunda road,4kalatani-kwa matolo-GNCA iiani.road 5.kwa kanzala -ivumbu-kakima-kwa saulo road | Tulimani | INFRA | Hard | New | 2,500,000.00 | 2026/2027 |
| 1618 | Kalakalya ECDE | Construction of 1 ECDE Classroom with an office and store, electric conduit, shelving to the stores, lockable metallic cabinet, wooden desk, wooden arm chairs, harvesting water tank, kiddy chairs and tables, play equipment. | Nguumo | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1874 | Roads maintenance of major roads | Roads maintenance of : 1. ngunini-kinyuani-ngwani-kwa kaviiu- kithuluni market. 2.kwa yindu -kanyenyoni road.3.wikiwu-kithetheni-muketani- mututungu road..4.kiliku-kyanziu-kwa katolo road.5. nguani drift | Tulimani | INFRA | Hard | New | 2,500,000.00 | 2026/2027 |
| 1619 | Tunguni ECDE | Construction of 1 ECDE Classroom with an office and store, electric conduit, shelving to the stores, lockable metallic cabinet, wooden desk, wooden arm chairs, harvesting water tank, kiddy chairs and tables, play equipment. | Nguumo | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1620 | Uvileni ECDE | Construction of 1 ECDE Classroom with an office and store, electric conduit, shelving to the stores, lockable metallic cabinet, wooden desk, wooden arm chairs, harvesting water tank, kiddy chairs and tables, play equipment. | Nguumo | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1621 | Ngiwa ECDE | Construction of 1 ECDE Classroom with an office and store, electric conduit, shelving to the stores, lockable metallic cabinet, wooden desk, wooden arm chairs, harvesting water tank, kiddy chairs and tables, play equipment. | Nguumo | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1622 | Ndovoini Dispensary Staff Quarter | Construction of Ndovoini Dispensary Staff Quarter. | Nguumo | HS | Hard | New | 2,500,000.00 | 2026/2027 |
| 1636 | Rehabilitation of kwa Makusa BH | Rehabilitation of kwa Makusa BH | Nguu/Masumba | WSI | Hard | Stalled | 2,500,000.00 | 2026/2027 |
| 1896 | Construction of Meliani Drift | Construction of Meliani Drift | Kako/Waia | INFRA | Hard | New | 2,500,000.00 | 2026/2027 |
| 1641 | Renovation of Mithumoni dispensary | Renovation of Mithumoni Dispensary | Nguu/Masumba | HS | Hard | New | 2,500,000.00 | 2026/2027 |
| 1900 | Road maintenance, improvement and light grading | Road maintenance, improvement and light grading | Kako/Waia | INFRA | Hard | New | 2,500,000.00 | 2026/2027 |
| 1907 | Imandini ECDE | Construction of one classroom, office, store and water tank and play equipment | Kithungo/Kitundu | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1908 | Mumani ECDE | Construction of one classroom, office, store and water tank and play equipment | Kithungo/Kitundu | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1909 | Woyani ECDE | Construction of one classroom, office, store and water tank and play equipment | Kithungo/Kitundu | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1910 | Kaseki ECDE | Construction of one classroom, office, store and water tank and play equipment | Kithungo/Kitundu | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1669 | Kavete-Kangii-Ngakaa road | bush clearing, road opening and heavy grading | Makindu | INFRA | Hard | New | 2,500,000.00 | 2026/2027 |
| 1673 | financial support to sacco.value chain development & vaccination compaign | access to credit &farm inputs 1m, value chain development (1m)& vaccination compaign 0.5m | Mtito Andei | AGRI | Soft | New | 2,500,000.00 | 2026/2027 |
| 1675 | ngiluni Ecde | construction of a class,office,store, playing equipment,10000 liters water tank, chairs & table's | Mtito Andei | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1676 | kivutini Ecde | construction of a class,office,store, playing equipment,10000 liters water tank, chairs & table's | Mtito Andei | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1677 | mikomani Ecde | construction of a class,office,store, playing equipment,10000 liters water tank, chairs & table's | Mtito Andei | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1684 | Timboni- Kitheini road | grading and gravelling | Ivingoni/Nzambani | INFRA | Hard | New | 2,500,000.00 | 2026/2027 |
| 1698 | Kaliani ecde | Construction of a classroom, office and store | Masongaleni | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1699 | Muangeni ecde | Construction of a classroom, office and store | Masongaleni | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1700 | Muliluni ecde | Construction of a classroom, office and store | Masongaleni | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1701 | Mweini ecde | Construction of a classroom, office and store | Masongaleni | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1470 | Kwambata ECDE | Construction of one classroom, office, store,electrical installation,shelving unit to store, one wooden desk, one wooden armchair, 10,000ltrs water tanks,20 kiddy cahirs and 10 kiddy tables | Kitise/Kithuki | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1471 | Waimu ECDE | Construction of one classroom, office, store,electrical installation,shelving unit to store, one wooden desk, one wooden armchair, 10,000ltrs water tanks,20 kiddy cahirs and 10 kiddy tables | Kitise/Kithuki | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1483 | Kathuma water project | Kwothuku water extension to Kathuma area | Mbitini | WSI | Hard | Phased | 2,500,000.00 | 2026/2027 |
| 1769 | Nguuni ECDE | Construction of one class room, store and office | Kasikeu | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1770 | Kitivo ECDE | Construction of one classroom, office and strore | Kasikeu | DIEI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1783 | Mukilitwa water project | Distribution,rising main and storage tank | Ilima | WSI | Hard | Ongoing | 2,500,000.00 | 2026/2027 |
| 1786 | Renovation of Kyenzenzeni Dispensary | Renovation of Kyenzenzeni Dispensary | Ilima | HS | Hard | New | 2,500,000.00 | 2026/2027 |
| 1532 | Kwa lili earth dam | Construction | Wote/Nziu | WSI | Hard | New | 2,500,000.00 | 2026/2027 |
| 1517 | support on cushioning farmers on mango produce and marketing | Cushion farmers on mango produce and marketing. | Mavindini | AGRI | Soft | New | 2,400,000.00 | 2026/2027 |
| 1854 | Installation of drainage structures (Box Culverts) along Mweleli, Kamali and Kwa Ngyema Streams -RMLF | Installation of drainage structures (Box Culverts) along Mweleli, Kamali and Kwa Ngyema Streams -RMLF | Kalawa | INFRA | Hard | — | 2,300,000.00 | 2026/2027 |
| 1894 | Waia Earth Dam: Rehabilitation and further distribution to Wambiti AIC Church, Comprehensive School, Dispensary , Secondary School , Installation of Water Point Tank at Kyamangatu and Extension to Ngaakaa Market | Waia Earth Dam: Rehabilitation and further distribution to Wambiti AIC Church, Comprehensive School, Dispensary , Secondary School , Installation of Water Point Tank at Kyamangatu and Extension to Ngaakaa Market | Kako/Waia | WSI | Hard | New | 2,200,000.00 | 2026/2027 |
| 1662 | Sports Development- Ligi Mashinani | Ligi Mashinani - facilitation for sports through cash awards and equipments | Makindu | GCYSS | soft | New | 2,200,000.00 | 2026/2027 |
| 1545 | Kwa mwenga borehole | Rehabilitation of existing lines | Kikumini/Muvau | WSI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1801 | Kikoko Market shed | Construction of market shed | Kilungu | TRD | Hard | New | 2,000,000.00 | 2026/2027 |
| 1547 | Ivuto earthdam | Desilting of earthdam | Kikumini/Muvau | WSI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1806 | Makutano/ mwanyani/ St Lucia/ Kyangonye | Murriming and structures | Kilungu | INFRA | Hard | Existing | 2,000,000.00 | 2026/2027 |
| 1552 | Road improvement | Opening,grading, muramming | Kikumini/Muvau | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1554 | Construction of ECDE Toilets at Kalamba, Kilili, Kwa Kalui and Matiliku ECDE Centres each @ 500,000 | Construction of 2 door toilets in each ECDE Centre | Nzaui/Kilili/Kalamba | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1813 | Nunguni market planning | Survey and planning the Nunguni market | Kilungu | LAN | Soft | New | 2,000,000.00 | 2026/2027 |
| 1561 | Kwa Nduli water sump | Solarization and distribution | Nzaui/Kilili/Kalamba | WSI | Hard | Existing | 2,000,000.00 | 2026/2027 |
| 1817 | Kaumoni HGM ECDE | Construction of one classroom and office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1818 | Kyau Primary ECDE | Construction of classroom and office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1819 | Muiu DEB ECDE | Construction of one classroom and office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1821 | Kaiti ACK ECDE | Construction of one classroom, office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1823 | Kinyuani ECDE | Construction of classroom and an office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1824 | Kyamuthei ECDE | Construction of classroom and office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1825 | Ikangaani water project | Construction of 100m3 samp tank, water pump, connect to rising main, CCTV and security light at the power house and distribution to Kaseveni | Ukia | WSI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1826 | Kiukuni Primary ECDE | Construction of classroom and office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1827 | Nthimbani dispensary | Extension (pharmacy, immunization room-CWC and procedure room) and fencing | Ukia | HS | Hard | New | 2,000,000.00 | 2026/2027 |
| 1828 | Kwa wewa-Kithukuni-King'oi-Kwa Nzoka road opening | Opening of road | Ukia | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1829 | Makongo Special ECDE | Construction of classroom and office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1830 | Nthongoni ECDE | Construction of classroom and office | Ukia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1576 | ligi mashinani | Ligi mashinani | Kikumbulyu North | GCYSS | Soft | New | 2,000,000.00 | 2026/2027 |
| 1584 | Construction of ECDE classroom at Mikauni | Construction of ECDE classroom at Mikauni | Kikumbulyu North | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1841 | Fuel for road opening using the ward wheel loader machine | Fuel for road opening using the ward wheel loader,operator and supervision facilitation. | Kee | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1843 | School feeding programme | School feeding programme | Kee | DIEI | Soft | Ongoing | 2,000,000.00 | 2026/2027 |
| 1857 | Equipping of Katangini Maternity | Equipping of maternity | Kalawa | HS | Hard | Phased | 2,000,000.00 | 2026/2027 |
| 1603 | Civic Education | capacity building programme | Kikumbulyu South | DEV | Soft | New | 2,000,000.00 | 2026/2027 |
| 1861 | Opening of 5 No. Acess roads; Kwa Kavavu-Mutinda Noa, Kwa ngului-Simon mwangangi, Thwake Pri-Kwa Nzimbii, Kinyau Dispensary-Kalima-Thwake River, Kakuli-Kitana,Ndauni | Opening 5 No. access roads | Kalawa | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1607 | Tutini water project | Electrification, rehabilitation,flushing,test pumping and water tank | Emali/Mulala | WSI | Hard | Ongoing | 2,000,000.00 | 2026/2027 |
| 1865 | Mango purchase through Kalawa Sacco | Funding Kalawa Sacco to purchase mangoes | Kalawa | AGRI | Soft | New | 2,000,000.00 | 2026/2027 |
| 1866 | Roads routine maintainance | Routine maintainance of roads | Kalawa | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1872 | Mulima Water Project | repair works of the distribution line | Tulimani | WSI | Hard | Phased | 2,000,000.00 | 2026/2027 |
| 1897 | Kako St. PatrickS VTC: Renovation and re-roofing of the tuition block | Kako St. PatrickS VTC: Renovation and re-roofing of the tuition block | Kako/Waia | DIEI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1643 | Road opening | Road opening | Nguu/Masumba | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1644 | Road opening | Road opening | Nguu/Masumba | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1901 | Sports Development:Ligi Mashinani | Sports Development:Ligi Mashinani | Kako/Waia | GCYSS | soft | New | 2,000,000.00 | 2026/2027 |
| 1906 | Mutooni water project | Distribution to Mutooni village and Kithungo market- (3Km) | Kithungo/Kitundu | WSI | Hard | Phased | 2,000,000.00 | 2026/2027 |
| 1913 | Ligi Mashinani | Ligi Mashinani | Kithungo/Kitundu | GCYSS | soft | New | 2,000,000.00 | 2026/2027 |
| 1919 | Kikima Water Project | Pipeline extensionfrom Kivandini chiefs office toKikima market, reticulation | Mbooni | WSI | Hard | Ongoing | 2,000,000.00 | 2026/2027 |
| 1922 | Roads opening programme | Bush clearing and opening of access roads in the ward | Mbooni | INFRA | Hard | Ongoing | 2,000,000.00 | 2026/2027 |
| 1925 | Rehabilitation of Kyangoma playing ground | Stone pitching,fencing & greening | Mbooni | GCYSS | soft | Ongoing | 2,000,000.00 | 2026/2027 |
| 1679 | mtito Andei hospital | pit latrine for outpatient | Mtito Andei | HS | Hard | Phased | 2,000,000.00 | 2026/2027 |
| 1936 | Distribution of Kinze Earth dam water project | Return line distribution from no. 8 market to source | Kisau/Kiteta | WSI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1939 | Distribution of Songeni B/H water | Elevated steel tower tank distribution & return distribution | Kisau/Kiteta | WSI | Hard | Phased | 2,000,000.00 | 2026/2027 |
| 1685 | Makokani- Matulani road | Grading and gravelling | Ivingoni/Nzambani | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1704 | Feeder roads opening,grading and culvert construction | Feeder roads opening,grading and culvert construction | Masongaleni | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1705 | LIGI MASHINANI AND MARCHING GRANT | LIGI MASHINANI AND MARCHING GRANT | Masongaleni | GCYSS | soft | New | 2,000,000.00 | 2026/2027 |
| 1707 | Kwa Nzuna Earth dam | Desilting | Thange | WSI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1719 | certified seeds(maize) | supply of certified seeds (maize) in the ward | Mukaa | AGRI | Soft | New | 2,000,000.00 | 2026/2027 |
| 1467 | Maaueli dispensary | construction of incinerator,septic pit, construction of staff toilet , wiring and dropping of electricity | Kitise/Kithuki | HS | Hard | New | 2,000,000.00 | 2026/2027 |
| 1728 | kwa kalomi- usi unene road | construction of drift | Mukaa | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1477 | Ward farmers SACCO | ward farmers sacco to be funded | Kitise/Kithuki | AGRI | Soft | New | 2,000,000.00 | 2026/2027 |
| 1482 | Kyemundu playground | Installation of culverts and drainage system | Mbitini | GCYSS | Hard | Stalled | 2,000,000.00 | 2026/2027 |
| 1489 | Kavuthu market lighting | Floodlight installation ( mulika mwizi) | Mbitini | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1495 | Kyemole-Kasambani-Itumbule-Mwisa-Yoani-Kateiko-Kithoni- Kwa mtumishi- Ikaasu junction | Road opening and grading | Kathonzweni | INFRA | Hard | New | 2,000,000.00 | 2026/2027 |
| 1500 | Abattoir land | Purchase of abattoir land- Additional funds | Kathonzweni | CA | Hard | Phased | 2,000,000.00 | 2026/2027 |
| 1511 | Nthunguni borehole water project | Distribution line from source to Nthunguni | Mavindini | WSI | Hard | Non operational | 2,000,000.00 | 2026/2027 |
| 1512 | Kitumbai borehole water project | Operationalization of the borehole | Mavindini | WSI | Hard | Non operational | 2,000,000.00 | 2026/2027 |
| 1513 | Ilumani borehole water project | Drilling of borehole. | Mavindini | WSI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1524 | Ligi mashinani | ligi mashinani | Mavindini | GCYSS | Soft | New | 2,000,000.00 | 2026/2027 |
| 1534 | Kiti-kyumu to kivandini pipeline | Pipeline extension | Wote/Nziu | WSI | Hard | New | 2,000,000.00 | 2026/2027 |
| 1535 | Ligi mashinani | Sports attire, balls, cash awards, allowances for ball players and referees | Wote/Nziu | GCYSS | Hard | New | 2,000,000.00 | 2026/2027 |
| 1791 | Levelling of Kitundumo /Isovya Playground | Levelling of playground | Ilima | GCYSS | hard | New | 2,000,000.00 | 2026/2027 |
| 1573 | Contracted staff for: Kisayani health center, Kathyaka heath center and Kiaoni Health center | Contracted staff for: Kisayani health center, Kathyaka heath center and Kiaoni Health center | Kikumbulyu North | HS | Soft | New | 1,800,000.00 | 2026/2027 |
| 1832 | Road grading | Road grading | Ukia | INFRA | Hard | New | 1,750,000.00 | 2026/2027 |
| 1659 | Yiiani REREC project | Power distribution/Transformer maximization | Makindu | INFRA | Hard | Ongoing | 1,700,000.00 | 2026/2027 |
| 1465 | Kwa Nzeki/Makovo earthdam | Reshaping of embarkment and spill way (earthworks), concrete wall and expansion | Kitise/Kithuki | WSI | Hard | Stalled | 1,700,000.00 | 2026/2027 |
| 1790 | support to ligi mashinani | support to ligi mashinani | Ilima | GCYSS | soft | New | 1,650,000.00 | 2026/2027 |
| 1656 | Rehabilitation of Katheani Borehole | Borehole flashing,water quality analysis,camera inspection,test pumping,installation of water pump, solarization, fencing and distribution to existing water kiosk at katheani market | Makindu | WSI | Hard | — | 1,600,000.00 | 2026/2027 |
| 1557 | Kwa Kilungu drift | Construction of a drift | Nzaui/Kilili/Kalamba | INFRA | Hard | New | 1,500,000.00 | 2026/2027 |
| 1822 | Mumbuni Sand Dam | Construction of sand dam | Ukia | WSI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1567 | Purchase of surgical implants | Supply of Surgical implats | Nzaui/Kilili/Kalamba | HS | Soft | New | 1,500,000.00 | 2026/2027 |
| 1585 | Kilui water project | Rehabilitation of Kilui return line [two kiosks,two water tanks and platforms] | Kikumbulyu South | WSI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1586 | Kilui water project | Water extension from Beria to Kirinyanga and from siembeni to ngolomoki | Kikumbulyu South | WSI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1588 | Extension of streetlights from Posta to Bridge | Streetlights and floodlights | Kikumbulyu South | INFRA | Hard | New | 1,500,000.00 | 2026/2027 |
| 1590 | Road routine maintainance | Road works | Kikumbulyu South | INFRA | Hard | New | 1,500,000.00 | 2026/2027 |
| 1593 | Mikuyuni ECDE Class | Construction of an ECDE Class | Kikumbulyu South | DIEI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1594 | Mukelenzuni ECDE Toilet | Construction of an ECDE toilet,levelling of the ground and fencing | Kikumbulyu South | DIEI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1628 | Ligi Mashinani | Support to grassroot sports devlopment through Ligi Mashinani | Nguumo | GCYSS | soft | Ongoing | 1,500,000.00 | 2026/2027 |
| 1640 | Construction of administration block at Masumba vocational Training Institute | Construction of administration block at Masumba vocational Training Institute | Nguu/Masumba | DIEI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1642 | Equiping of Matutu dispensary | Equiping of Matutu dispensary | Nguu/Masumba | HS | Hard | New | 1,500,000.00 | 2026/2027 |
| 1650 | Completion of Masumba market | Completion of Masumba malikiti | Nguu/Masumba | TRD | Hard | Stalled | 1,500,000.00 | 2026/2027 |
| 1661 | Youth empowerment and development programme- Ujuzi teke teke | Training of youths at Kisingo VTC and provision of tools of work | Makindu | GCYSS | soft | New | 1,500,000.00 | 2026/2027 |
| 1929 | Sports development programme | support sports activities in the ward | Mbooni | GCYSS | soft | Ongoing | 1,500,000.00 | 2026/2027 |
| 1680 | Athi kamunyi health center | fencing &staff quarter | Mtito Andei | HS | Hard | Phased | 1,500,000.00 | 2026/2027 |
| 1941 | Ndituni water project Fencing | Surveying and catchment concrete posts fencing | Kisau/Kiteta | LAN | Hard | New | 1,500,000.00 | 2026/2027 |
| 1686 | Kamunyuni- Kwa Ngutu drift | construction of culverts | Ivingoni/Nzambani | INFRA | Hard | New | 1,500,000.00 | 2026/2027 |
| 1691 | Ligimashinani | — | Ivingoni/Nzambani | GCYSS | soft | New | 1,500,000.00 | 2026/2027 |
| 1712 | Ajira kwa Vijana, Ligi Mashinani, PWDs/Elderly/Women Enhancement | Enhancement | Thange | GCYSS | soft | New | 1,500,000.00 | 2026/2027 |
| 1715 | Civic Education & community driven disaster management and preparedness | Enhancement | Thange | DEV | Soft | New | 1,500,000.00 | 2026/2027 |
| 1721 | ligi Mashinani | facilitation for players, uniforms, training for coaches | Mukaa | GCYSS | soft | Ongoing | 1,500,000.00 | 2026/2027 |
| 1472 | Youth empowerment | Youth empowerment programmes | Kitise/Kithuki | GCYSS | Soft | New | 1,500,000.00 | 2026/2027 |
| 1486 | Sports development-Ligi Mashinani | Facilitation for sports through cash awards and equipments | Mbitini | GCYSS | Soft | New | 1,500,000.00 | 2026/2027 |
| 1744 | Ligi mashinani, Gender, Children,Youth,Sports and Social Services, ujuzi teketeke | Facilitation | Kiima Kiu/Kalanzoni | GCYSS | soft | New | 1,500,000.00 | 2026/2027 |
| 1497 | Ligi mashinani | Support to sporting activities | Kathonzweni | GCYSS | Soft | New | 1,500,000.00 | 2026/2027 |
| 1755 | Mbiini borehole | Water distribution to mbiini market, kwa ngoma to yimbani | Kasikeu | WSI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1757 | Lumu dispensary | Constructtion of a fence, gate , staff quarters, electrification | Kasikeu | HS | Hard | New | 1,500,000.00 | 2026/2027 |
| 1758 | kwale level 3 hospital | Fencing, gate and Ashpit | Kasikeu | HS | Hard | New | 1,500,000.00 | 2026/2027 |
| 1765 | Fuel for machines | Fuel | Kasikeu | INFRA | Hard | New | 1,500,000.00 | 2026/2027 |
| 1510 | Athi mavindini water project | Operationalization of the water project | Mavindini | WSI | Hard | Non operational | 1,500,000.00 | 2026/2027 |
| 1768 | Fuel for machines | Fuel | Kasikeu | INFRA | Hard | New | 1,500,000.00 | 2026/2027 |
| 1771 | Kitumbini CCTI | Construction of a domitory | Kasikeu | DIEI | Hard | New | 1,500,000.00 | 2026/2027 |
| 1519 | Miangeni Dispensary | Renovation of the dispensary | Mavindini | HS | Hard | New | 1,500,000.00 | 2026/2027 |
| 1776 | Social protection, youth empowerment, talent development | Sports, PWD Mapping & Registrationt, ujuzi teketeke, elderly empowerement talent empowerement | Kasikeu | GCYSS | soft | New | 1,500,000.00 | 2026/2027 |
| 1777 | Social protection, youth empowerment, talent development | Sports, PWD Mapping & Registrationt, ujuzi teketeke, elderly empowerement talent empowerement | Kasikeu | GCYSS | soft | New | 1,500,000.00 | 2026/2027 |
| 1782 | Kwa Mwilu water project | solarization and distribution | Ilima | WSI | Hard | Ongoing | 1,500,000.00 | 2026/2027 |
| 1658 | Equipping of Kisingo VTC workshop | Equipping of the workshop with computers, shelves,network/WIFI accessories, Printer, furniture (chairs and executive tables) | Makindu | DIEI | Hard | Ongoing | 1,300,000.00 | 2026/2027 |
| 1739 | Kavuko maternity | Equiping | Kiima Kiu/Kalanzoni | HS | Hard | Stalled | 1,300,000.00 | 2026/2027 |
| 1778 | Ngokomi, Kiungwani, Mateso market | Construction o flood lights/ street lights | Kasikeu | TRD | Hard | New | 1,050,000.00 | 2026/2027 |
| 1536 | Licencing and training of motor vehicle and boda boada to the youth | Training and licensing | Wote/Nziu | GCYSS | Soft | New | 1,000,000.00 | 2026/2027 |
| 1537 | Entreprenuership grants to 10-youth groups (one group per cluster) | Entrenuership grant of hundred thousand (100,000) for every cluster group | Wote/Nziu | GCYSS | Soft | New | 1,000,000.00 | 2026/2027 |
| 1793 | Civic education and sentitisation | Civic education and sentitisation of development committees | Ilima | DEV | Soft | New | 1,000,000.00 | 2026/2027 |
| 1539 | Community feedback/ engagement | Feedback forums/ trainings | Wote/Nziu | DEV | Soft | New | 1,000,000.00 | 2026/2027 |
| 1802 | Ligi mashinani | Support ligi mashinani | Kilungu | GCYSS | soft | Ongoing | 1,000,000.00 | 2026/2027 |
| 1804 | Feeding progarm | Provision of food to ECDE pupils | Kilungu | DIEI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1550 | Westngosi dispensary | Renovation and equpping of labaratory | Kikumini/Muvau | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1551 | Kilisa dispensary | Renovation of staff quarters | Kikumini/Muvau | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1555 | Issuance of bursary | Bursuary Issuance to needy learners | Nzaui/Kilili/Kalamba | DIEI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1811 | Feeding progarm | Provision of food to ECDE pupils | Kilungu | DIEI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1812 | Ligi mashinani | Support ligi mashinani | Kilungu | GCYSS | soft | Ongoing | 1,000,000.00 | 2026/2027 |
| 1816 | Ukia dispensary | Renovation (roofing, tiling, painting) and placenta pit | Ukia | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1562 | Ligi mashinani | Sports development | Nzaui/Kilili/Kalamba | GCYSS | Soft | New | 1,000,000.00 | 2026/2027 |
| 1820 | Ikalyoni dispensary | Renovation(roofing, painting and tiling) | Ukia | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1569 | Kasekeleni water connection and Ndetani-Ndovoini water connection | Kasekeleni water connection with 10,000L water tank, Ndetani -Ndovoini water connection with a 10,000L water tank at Kwa Nzinga | Kikumbulyu North | WSI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1570 | capacity building of CHPs | Capacity building on basic modules on skills development, refresher trainings | Kikumbulyu North | HS | Soft | New | 1,000,000.00 | 2026/2027 |
| 1571 | Equipping laboratory at kanyungu dispensary | Equipping laboratory at kanyungu dispensary | Kikumbulyu North | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1572 | fence and gate at Nthongoni dispensary | Fencing and gate at Nthongoni dispensary | Kikumbulyu North | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1575 | Provision of galla goats to PWDs | Provision of galla goats to PWDs | Kikumbulyu North | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1577 | ajira kwa vijana | ajira kwa vijana | Kikumbulyu North | GCYSS | Soft | New | 1,000,000.00 | 2026/2027 |
| 1578 | boda boda empowerment | repair kit for motorcycles | Kikumbulyu North | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1582 | civic education and capacity building of development committees | training and capacity building of development committees, civic education | Kikumbulyu North | DEV | Soft | New | 1,000,000.00 | 2026/2027 |
| 1587 | Kwa Rozina and Sukali drifts | Construction of drifts | Kikumbulyu South | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1844 | Ligi mashinani | Facilitation to sporting activities | Kee | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1589 | Kwa Munyoki Drift | Construction of a drift and gabions | Kikumbulyu South | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1845 | Driving training and issuance of licences | Training on driving and issuance of licences | Kee | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1849 | Equipping of Kyanduya VTC | Equipping with haidressing training equipment/tools and office laptop | Kee | DIEI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1852 | Nzalani drift and key wall | Construction of a drift and a Key wall | Kee | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1598 | PWDs Empowerment | Empowerment of PWDs through supply of Galla goats | Kikumbulyu South | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1599 | Ujuzi teketeke | Providing critical skills and tools to the youth | Kikumbulyu South | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1855 | Muambani ECDE | Construction of ECDE Classroom | Kalawa | DIEI | Hard | — | 1,000,000.00 | 2026/2027 |
| 1600 | SACCO | Support to Kikumbulyu South farmers SACCO | Kikumbulyu South | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1856 | Mutembuku ECDE | Construction of ECDE Classroom | Kalawa | DIEI | Hard | — | 1,000,000.00 | 2026/2027 |
| 1601 | Market cleaners | Recruitment of more market cleaners | Kikumbulyu South | TRD | Soft | New | 1,000,000.00 | 2026/2027 |
| 1858 | Ngunini Borehole | Installation of New pump and motor, Borehole flushing, camera inspection and pipelines rehabilitation . | Kalawa | WSI | Hard | Stalled | 1,000,000.00 | 2026/2027 |
| 1867 | Ligi Mashinani | Ligi mashinani | Kalawa | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1617 | Kwa Ngala Borehole | Rehabilitation of Kwa Ngala Borehole | Nguumo | WSI | Hard | Stalled | 1,000,000.00 | 2026/2027 |
| 1623 | Waiting Bay and solarization of Ilatu Health Centre | Construction of a waiting Bay and solarization of Ilatu Health Centre | Nguumo | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1881 | Ligi mashinani | Ligi mashinani | Tulimani | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1626 | Support to Nguumo SACCO | Support to Nguumo SACCO | Nguumo | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1627 | Support to Youths for Ujuzi teketeke | Support to Youths for Ujuzi teketeke | Nguumo | GCYSS | soft | Ongoing | 1,000,000.00 | 2026/2027 |
| 1629 | Construction of Syumile Market toilet | Construction of Syumile Market toilet | Nguumo | TRD | Hard | New | 1,000,000.00 | 2026/2027 |
| 1887 | Ligi mashinani | Ligi mashinani | Tulimani | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1632 | Kwa Kathoka Electrification(REREC) | Kwa Kathoka Electrification(REREC) | Nguumo | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1633 | Culverts/Gabions at Mbiu Nzau hill and Mukononi River | Culverts/Gabions at Mbiu Nzau hill and Mukononi River | Nguumo | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1890 | Land Clinics and Successions | Land Clinics and Successions | Tulimani | CA | Soft | New | 1,000,000.00 | 2026/2027 |
| 1635 | Civic Education | Civic Education | Nguumo | DEV | Soft | New | 1,000,000.00 | 2026/2027 |
| 1899 | Kwa Mutombi Water project: Rehabiltation of the raising main | Kwa Mutombi Water project: Rehabiltation of the raising main | Kako/Waia | WSI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1645 | Road grading | Road grading | Nguu/Masumba | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1646 | Road grading | Road grading | Nguu/Masumba | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1647 | PWD(Provision of assessment and PWD devices) | Supportive devices and assessment | Nguu/Masumba | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1649 | Vaccination of dogs. | VCVB/FMD Rabies | Nguu/Masumba | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1911 | Utwiini dispensary | Equipping and operationalization of the laboratory | Kithungo/Kitundu | HS | Hard | Phased | 1,000,000.00 | 2026/2027 |
| 1660 | PWD economic empowerment programme | Income generating activities- poultry and goat rearing. | Makindu | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1917 | Civic education | Capacity building of the development committees | Kithungo/Kitundu | DEV | Soft | New | 1,000,000.00 | 2026/2027 |
| 1926 | Ukala CTTI | fencing, electrification and repairs | Mbooni | DIEI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1927 | Dairy development programme- subsidized AI services | Support to dairy farmers with subsidized Artificial insemination services | Mbooni | AGRI | Soft | Ongoing | 1,000,000.00 | 2026/2027 |
| 1928 | Crop development programme- Supply of certified seeds (maize and beans) | Supply of certified farm inputs-seeds (maize and beans) | Mbooni | AGRI | Soft | Ongoing | 1,000,000.00 | 2026/2027 |
| 1932 | Water harvesting-Path from poverty CBO | Support organized groups (Path from poverty ) with water tanks | Mbooni | GCYSS | soft | Ongoing | 1,000,000.00 | 2026/2027 |
| 1678 | Chps mobility | 147 biyscles and 2 motorcycle | Mtito Andei | HS | soft | New | 1,000,000.00 | 2026/2027 |
| 1943 | Supply of certified seeds | Maize - DK 8031 | Kisau/Kiteta | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1690 | Ujuziteketeke | — | Ivingoni/Nzambani | GCYSS | soft | New | 1,000,000.00 | 2026/2027 |
| 1694 | Civic Education | education | Ivingoni/Nzambani | DEV | Soft | New | 1,000,000.00 | 2026/2027 |
| 1696 | Nthongoni market skip bins | supply | Ivingoni/Nzambani | TRD | soft | New | 1,000,000.00 | 2026/2027 |
| 1711 | Ward Kit Waiver | Enhancement | Thange | HS | soft | New | 1,000,000.00 | 2026/2027 |
| 1469 | Matheani dispensary | Fencing and gate | Kitise/Kithuki | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1730 | Ngolosi Sand dam | desilting, construction of sump tank,installation pumping system, construction of storage tank and distribution line | Mukaa | WSI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1479 | Kitise stockyard | construction of rump, repairs and construction of gate | Kitise/Kithuki | TRD | Hard | New | 1,000,000.00 | 2026/2027 |
| 1735 | Extension Services | Climate smart training in agriculture and livestock, veterinary training | Kiima Kiu/Kalanzoni | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1741 | Kiimakiu dispensary lab. | Equiping, drinage, and renovation | Kiima Kiu/Kalanzoni | HS | Hard | Stalled | 1,000,000.00 | 2026/2027 |
| 1748 | Civic Education | Facilitation of Civic education forums and development committees | Kiima Kiu/Kalanzoni | DEV | Soft | New | 1,000,000.00 | 2026/2027 |
| 1749 | Lumu borehole | Water distribution from lumu borehole to kiou top dispensary and mitumani area | Kasikeu | WSI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1496 | Kiteei-Kwa Kalani-Kwa Katoo- Kwa Kaumba- Kwa Monyi- Kwa Maundu- Mutini- Mayuu- Ikaasu junction (Link to Kitise) | Road opening | Kathonzweni | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1752 | Kima borehole | Rehabilitation of the borehole | Kasikeu | WSI | Hard | Ongoing | 1,000,000.00 | 2026/2027 |
| 1753 | Mumela borehole | Drilling, equiping, and water distribution | Kasikeu | WSI | Hard | Stalled | 1,000,000.00 | 2026/2027 |
| 1754 | Mikuyu 2 water project | Installation of pumps, CCTV, repairing motor,water distribution | Kasikeu | WSI | Hard | Stalled | 1,000,000.00 | 2026/2027 |
| 1756 | Sultan Hamud Sub County Hospital | Fencing and gate to the mortuary | Kasikeu | HS | Hard | New | 1,000,000.00 | 2026/2027 |
| 1501 | Support to ward farmers SACCO | Support to ward farmers SACCO | Kathonzweni | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1503 | Kathonzweni VTC workshop- additional funds | Additional funds for construction of twin workshop at Kathonzweni VTC | Kathonzweni | DIEI | Hard | Phased | 1,000,000.00 | 2026/2027 |
| 1763 | Off mombasa road - Aic kwale-- Ndivu ECDE- Kima market- kwa kitaingi, kwa kitinio- kwa nyonga road | Grading | Kasikeu | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1764 | Off mombasa road - kwa malonza- kwa kitung'a road | Grading | Kasikeu | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1766 | Enguli- masive- ndungani- muua road | Concrete works | Kasikeu | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1767 | Makolongo- nthunguni-mbyani- kasokani, katulyani road | Opening | Kasikeu | INFRA | Hard | New | 1,000,000.00 | 2026/2027 |
| 1775 | Marketing and value addition | Formation of SACCOs, CIG, and FBOs | Kasikeu | AGRI | Soft | New | 1,000,000.00 | 2026/2027 |
| 1523 | Mavindini playground | Fence reinforcement and Basketball pitch construction | Mavindini | GCYSS | Hard | Phased | 1,000,000.00 | 2026/2027 |
| 1784 | Maintainance of water projects | Maintainance of water projects | Ilima | WSI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1533 | Pipeline extension; (i)from kavila iiuni (ii) from kiembeni to itandi | Pipeline extension | Wote/Nziu | WSI | Hard | New | 1,000,000.00 | 2026/2027 |
| 1794 | Kyangee CTTI | Equipping of the CTTI | Ilima | DIEI | Hard | New | 850,000.00 | 2026/2027 |
| 1882 | Ajira Mtaani | Ajira mtaani | Tulimani | GCYSS | soft | New | 850,000.00 | 2026/2027 |
| 1940 | Equiping of Kisau Sub county Hospital | Provision of Ultra sound machine at Kisau Sub county Hospital | Kisau/Kiteta | HS | Hard | New | 800,000.00 | 2026/2027 |
| 1831 | Ukia CTTI | Construction of toilet | Ukia | DIEI | Hard | New | 750,000.00 | 2026/2027 |
| 1833 | Road grading | Road grading | Ukia | INFRA | Hard | New | 750,000.00 | 2026/2027 |
| 1631 | Market security lights(Ilatu, Kalembe and Kaunguni) | Installation Market security lights(Ilatu, Kalembe and Kaunguni) | Nguumo | INFRA | Hard | New | 750,000.00 | 2026/2027 |
| 1835 | Youth-Ligi mashinani | Support to ligi mashinani | Ukia | GCYSS | soft | New | 700,000.00 | 2026/2027 |
| 1602 | Siembeni public toilet | Construction of a market pit toilet | Kikumbulyu South | TRD | Hard | New | 700,000.00 | 2026/2027 |
| 1612 | Ultra poor program | Support ton PWDs | Emali/Mulala | GCYSS | soft | New | 700,000.00 | 2026/2027 |
| 1912 | Kusyongali Fllodlight | Installation of floodlight | Kithungo/Kitundu | INFRA | Hard | New | 700,000.00 | 2026/2027 |
| 1733 | Kaangi borehole | Rehabilitation works | Kiima Kiu/Kalanzoni | WSI | Hard | Stalled | 700,000.00 | 2026/2027 |
| 1762 | Kasikeu health Center | Construction of outpatient toilet | Kasikeu | HS | Hard | New | 700,000.00 | 2026/2027 |
| 1903 | Vaccination of dogs and cows | Vaccination of dogs and cows | Kako/Waia | AGRI | Soft | New | 600,000.00 | 2026/2027 |
| 1668 | Routine road maintenance and improvement- fuel | Routine road maintenance and improvement- fuel | Makindu | INFRA | Hard | New | 600,000.00 | 2026/2027 |
| 1670 | Construction of Ngukuni ECDE toilet | Construction of Ngukuni ECDE toilet | Makindu | DIEI | Hard | New | 600,000.00 | 2026/2027 |
| 1720 | Rabies | purchase of vacine for rabies | Mukaa | AGRI | Soft | New | 600,000.00 | 2026/2027 |
| 1774 | Vaccination | Vaccination against Rabies, CCPP $ LCD | Kasikeu | AGRI | Soft | New | 540,000.00 | 2026/2027 |
| 1779 | Kayata,mbyani enguli,muambani, masokani, kitivo, mumela mkt | Construction of flood/street lights | Kasikeu | TRD | Hard | New | 510,000.00 | 2026/2027 |
| 1792 | PWD Mapping | Pwd mapping | Ilima | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1799 | Waiving bill | Waiving hospital bills for patients | Kilungu | HS | Soft | Ongoing | 500,000.00 | 2026/2027 |
| 1800 | Kyanganda staff quarter | Completion of staff quarter | Kilungu | HS | Hard | Ongoing | 500,000.00 | 2026/2027 |
| 1803 | Ligi mashinani | Support ligi mashinani for PWDs | Kilungu | GCYSS | soft | Ongoing | 500,000.00 | 2026/2027 |
| 1805 | Civic Education | Civic education to the community | Kilungu | DEV | Soft | New | 500,000.00 | 2026/2027 |
| 1808 | Waiving medical bills | Clear medical bill for patients | Kilungu | HS | Soft | Ongoing | 500,000.00 | 2026/2027 |
| 1809 | Kaia Health centre | Fencing completion | Kilungu | HS | Hard | Existing | 500,000.00 | 2026/2027 |
| 1814 | Ligi mashinani | Support ligi mashinani for PWDs | Kilungu | GCYSS | soft | Ongoing | 500,000.00 | 2026/2027 |
| 1564 | Supply of Manure | Supply of inputs to farmers | Nzaui/Kilili/Kalamba | AGRI | Soft | New | 500,000.00 | 2026/2027 |
| 1565 | Support to ward agricultural Sacco | Financial support to farmers in the sacco | Nzaui/Kilili/Kalamba | AGRI | Soft | New | 500,000.00 | 2026/2027 |
| 1834 | Youth-Ligi mashinani | Support to ligi mashinani | Ukia | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1579 | economic empowerment to special youth groups | economic empowerment to special youth groups | Kikumbulyu North | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1836 | Youth empowerment-uji teke teke | Ujuzi teketeke | Ukia | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1846 | PWD Empowerment | PWD economic empowerment | Kee | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1847 | Social inclusion and public health advancement | Social inclusion and public health advancement for the youth | Kee | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1851 | Equipping of Kyanduya social hall | Equipping with plastic chairs | Kee | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1864 | Kalawa Sub County Hospital Incinerator | Construction of an incinerator | Kalawa | HS | Hard | New | 500,000.00 | 2026/2027 |
| 1868 | Civic education | Training of Community Development Committees (CDCs) | Kalawa | DEV | Soft | New | 500,000.00 | 2026/2027 |
| 1613 | Youth empowerment- business start up support | Support youth initiatives e.g car wash machines | Emali/Mulala | GCYSS | soft | Ongoing | 500,000.00 | 2026/2027 |
| 1877 | Iiani Dspensary | Renovation of Iiani Dispensary | Tulimani | HS | Hard | Phased | 500,000.00 | 2026/2027 |
| 1883 | Youth Empowerment | Youth Empowerment | Tulimani | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1888 | Ajira Mtaani | Ajira mtaani | Tulimani | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1889 | Youth Empowerment | Youth Empowerment | Tulimani | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1902 | PWD Support: provision of Assistive devices | PWD Support: provision of Assistive devices | Kako/Waia | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1648 | Promotion of cultural groups | Promotion of cultural groups | Nguu/Masumba | TRD | soft | New | 500,000.00 | 2026/2027 |
| 1651 | Construction of Vololo Toilets | Construction of Vololo Toilets | Nguu/Masumba | TRD | Hard | New | 500,000.00 | 2026/2027 |
| 1652 | Physical planning | Masumba market physical planning | Nguu/Masumba | LAN | Soft | New | 500,000.00 | 2026/2027 |
| 1653 | Planning at Makutano market | Physical planning of Makutano market | Nguu/Masumba | LAN | Soft | New | 500,000.00 | 2026/2027 |
| 1654 | Civic education | Civic education | Nguu/Masumba | DEV | Soft | New | 500,000.00 | 2026/2027 |
| 1914 | PWDS empowerment | Support with income generating activities | Kithungo/Kitundu | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1663 | Civic Education Programme | Civic education, community outreach and community feedback forums, trainings and sensitizations | Makindu | DEV | Soft | New | 500,000.00 | 2026/2027 |
| 1920 | Wathi water Project | Rehabilitation/replacement of broken pipes | Mbooni | WSI | Hard | Non operational | 500,000.00 | 2026/2027 |
| 1930 | Youth empowerment programme- Poultry support to Mbooni youth in Agri business | Provision of damliner and Poultry support to Mbooni youth in Agri business | Mbooni | GCYSS | soft | Ongoing | 500,000.00 | 2026/2027 |
| 1931 | Youth empowerment programme- MKJ program | MKJ program/Ujuzi teketeke | Mbooni | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1933 | PWD empowerment programme | Provision of assistive devices such as wheel chairs and clutches | Mbooni | GCYSS | soft | Ongoing | 500,000.00 | 2026/2027 |
| 1934 | Civic education programme | Training of development committees | Mbooni | DEV | Soft | New | 500,000.00 | 2026/2027 |
| 1681 | mapping PWD's/Elderly | mapping of PWD's/elderly | Mtito Andei | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1937 | Rehabilitation of Kwa Matinga B/H | Motor replacement & B/H Flushing | Kisau/Kiteta | WSI | Hard | Non operational | 500,000.00 | 2026/2027 |
| 1942 | Equiping of Kisau Sub county Hospital | Provision of a Dental Chair at Kisau Sub county Hospital | Kisau/Kiteta | HS | soft | New | 500,000.00 | 2026/2027 |
| 1944 | Supply of Mango friut fly baits | Supply of Mango friut fly baits | Kisau/Kiteta | AGRI | Soft | New | 500,000.00 | 2026/2027 |
| 1693 | Electricity connection at Ward administrators office | Electrification | Ivingoni/Nzambani | DEV | Hard | New | 500,000.00 | 2026/2027 |
| 1949 | Installation of floodlights at Muluti, Ndivuni (near Mbooni SCA's Office) and Ngaa shopping centers | Installation of floodlights at Muluti, Ndivuni (near Mbooni SCA's Office) and Ngaa shopping centers | Kisau/Kiteta | TRD | Hard | New | 500,000.00 | 2026/2027 |
| 1695 | Migingo parking | Upgrading | Ivingoni/Nzambani | TRD | Hard | New | 500,000.00 | 2026/2027 |
| 1713 | PWDs/Elderly/Women Empowerment | Enhancement | Thange | GCYSS | soft | New | 500,000.00 | 2026/2027 |
| 1716 | Urban Planning | Physical planning in Usalama and Manyanga Markets | Thange | TRD | Soft | New | 500,000.00 | 2026/2027 |
| 1717 | Tittle deeds | Titling of land in Utiithi sub ward | Thange | LAN | Soft | New | 500,000.00 | 2026/2027 |
| 1718 | Vacination of dogs | Vacination of dogs | Thange | AGRI | Soft | New | 500,000.00 | 2026/2027 |
| 1473 | PWDs support | support to PWDs | Kitise/Kithuki | GCYSS | Soft | New | 500,000.00 | 2026/2027 |
| 1476 | Civic education | Civic education,Community outreach and community feedback forums, trainings and sensitization | Kitise/Kithuki | DEV | Soft | New | 500,000.00 | 2026/2027 |
| 1478 | Provision for vaccines against rabbies | Purchase of the vaccines, facilitation of service providers, publicizing | Kitise/Kithuki | AGRI | Soft | New | 500,000.00 | 2026/2027 |
| 1480 | Yinthungu CTTI | renovation of classrooms | Kitise/Kithuki | DIEI | Hard | New | 500,000.00 | 2026/2027 |
| 1738 | Ilawani drift | constructin of drift | Kiima Kiu/Kalanzoni | INFRA | Hard | New | 500,000.00 | 2026/2027 |
| 1485 | Rabbies vaccination. | Dogs vaccination against rabbies | Mbitini | AGRI | Soft | New | 500,000.00 | 2026/2027 |
| 1750 | Muatineni borehole | Grid, connection | Kasikeu | WSI | Hard | New | 500,000.00 | 2026/2027 |
| 1751 | Kisaulu Borehole | Rehabilitation off the borehole,Water distribution from kisaulu borehole to Kandolo primary school | Kasikeu | WSI | Hard | New | 500,000.00 | 2026/2027 |
| 1498 | PWD support | PWD economic empowerment | Kathonzweni | GCYSS | Soft | New | 500,000.00 | 2026/2027 |
| 1499 | Psychosocial support programme | Psychosocial support for youth | Kathonzweni | GCYSS | Soft | New | 500,000.00 | 2026/2027 |
| 1502 | Civic education | Civic education | Kathonzweni | DEV | Soft | New | 500,000.00 | 2026/2027 |
| 1760 | Muua dispensary | Renovation of the laboratory | Kasikeu | HS | Hard | New | 500,000.00 | 2026/2027 |
| 1507 | Electrification of Mutini health centre | Electrification of Mutini health centre | Kathonzweni | HS | Hard | New | 500,000.00 | 2026/2027 |
| 1508 | Kathamboni borehole- additional funds | Additional funds for completion of the borehole equipping | Kathonzweni | WSI | Hard | Phased | 500,000.00 | 2026/2027 |
| 1772 | Vaccination | Vaccination against Rabies, CCPP $ LCD | Kasikeu | AGRI | Soft | New | 500,000.00 | 2026/2027 |
| 1521 | PWD empowerment | PWD economic empowerment(100 seater tents and PA system. | Mavindini | GCYSS | Soft | New | 500,000.00 | 2026/2027 |
| 1522 | PWD sports | PWD sports | Mavindini | GCYSS | Soft | New | 500,000.00 | 2026/2027 |
| 1526 | Kavingo borehole | Installation/replacement of pump set | Wote/Nziu | WSI | Hard | Stalled | 500,000.00 | 2026/2027 |
| 1563 | PWDs empowerment | PWDs start up capital | Nzaui/Kilili/Kalamba | GCYSS | Soft | New | 400,000.00 | 2026/2027 |
| 1869 | Kalawa Ward Office power installation | Installation of electricity at the ward office | Kalawa | INFRA | Hard | New | 400,000.00 | 2026/2027 |
| 1838 | PWD Empowerment | Support to PWDs economic empowerment | Ukia | GCYSS | soft | New | 300,000.00 | 2026/2027 |
| 1616 | Kitamanduni cultural festival | Support cultural activities | Emali/Mulala | GCYSS | soft | New | 300,000.00 | 2026/2027 |
| 1918 | Kinyansye Sub ward | Fencing of the dispensary | Kithungo/Kitundu | HS | Hard | New | 300,000.00 | 2026/2027 |
| 1740 | Ulu dispensary | Power connection | Kiima Kiu/Kalanzoni | HS | Hard | Stalled | 300,000.00 | 2026/2027 |
| 1747 | Mbondoni cattle dip (kwa Mating'a) | Rehabilitation works | Kiima Kiu/Kalanzoni | TRD | Hard | Stalled | 300,000.00 | 2026/2027 |
| 1761 | Nduluni dispensary | Fencing and gate | Kasikeu | HS | Hard | New | 300,000.00 | 2026/2027 |
| 1837 | PWD-paralympic | Support to paralympics | Ukia | GCYSS | soft | New | 250,000.00 | 2026/2027 |
| 1878 | Mapping of PWD's | Mapping of PWD's | Tulimani | GCYSS | soft | New | 250,000.00 | 2026/2027 |
| 1880 | Elderly Support | Elderly Support | Tulimani | GCYSS | soft | New | 250,000.00 | 2026/2027 |
| 1884 | Mapping of PWD's | Mapping of PWD's | Tulimani | GCYSS | soft | New | 250,000.00 | 2026/2027 |
| 1630 | Syumile Security Lights | Installation of Syumile Security Lights | Nguumo | INFRA | Hard | New | 250,000.00 | 2026/2027 |
| 1886 | Elderly Support | Elderly Support | Tulimani | GCYSS | soft | New | 250,000.00 | 2026/2027 |
| 1745 | Nzeveni mrkt flood light | Flood light installation | Kiima Kiu/Kalanzoni | TRD | Hard | New | 250,000.00 | 2026/2027 |
| 1746 | Ngiini market flood light | Flood light installation | Kiima Kiu/Kalanzoni | TRD | Hard | New | 250,000.00 | 2026/2027 |
| 1780 | Civic Education | Community Outreach and awareness | Kasikeu | DEV | Soft | New | 250,000.00 | 2026/2027 |
| 1781 | Civic Education | Community Outreach and awareness | Kasikeu | DEV | Soft | New | 250,000.00 | 2026/2027 |
| 1558 | Survey of roads before opening at disputed areas | Surey of roads | Nzaui/Kilili/Kalamba | LAN | Soft | New | 200,000.00 | 2026/2027 |
| 1566 | Vaccination of dogs against rabies | Vaccination drive against rabies | Nzaui/Kilili/Kalamba | AGRI | Soft | New | 200,000.00 | 2026/2027 |
| 1574 | Equipping of Kathyaka healthcare facility maternity | Equipping of Kathyaka healthcare facility maternity | Kikumbulyu North | HS | Hard | New | 200,000.00 | 2026/2027 |
| 1759 | Masokani dispensary | Construction of laboratory | Kasikeu | HS | Hard | Ongoing | 200,000.00 | 2026/2027 |
| 1773 | Marketing and value addition | Formation of SACCOs, CIG, and FBOs | Kasikeu | AGRI | Soft | New | 200,000.00 | 2026/2027 |
| 1879 | Huduma mashinani | Huduma mashinani | Tulimani | GCYSS | soft | New | 150,000.00 | 2026/2027 |
| 1885 | Huduma mashinani | Huduma mashinani | Tulimani | GCYSS | soft | New | 150,000.00 | 2026/2027 |
| 1946 | Repairs and supply of acaricides at Ngoni cattle dip | Repairs and supply of acaricides at Ngoni cattle dip | Kisau/Kiteta | AGRI | Hard | New | 100,000.00 | 2026/2027 |
| 1491 | Mutyambua Library | Mantainance of the library | Mbitini | DIEI | Hard | New | 50,000.00 | 2026/2027 |